Preliminary phase : Site preparation.
The first step was to dispose of the more than 30 tons of debris from the crashed roof, the walls erosion, and damaged broken wood. This having unveiled the great potential of restoration of the site, the next step was to do the immediately needed repairs to walls, windows, and to install an entry door to restrict unauthorized access to the site.
Debris of crashed roof and damaged woood.
Replacing of a disappeared beam, crucial to the support of the structural columns
Temporary safety ramp in the Ladies Gallery
Protective closing of windows with polyane
An official ‘Jewish Heritage site’ sign posted on the new synagogue entry door.
>>Next : New roof construction